PROJECTS
SAN RAMON VALLEY USD
Phase 1 - 3.4 MW Solar PV, Operational Assistance
Phase 2 - 3.3 MW Solar PV, Full Project Implementation
Canopy and Roof Mounted PV on 16 District Sites
Phase 2 Operational End of 2016
$13 Million Capital Cost, CREBs Funded
BACKGROUND
In 2012, Sage was selected by the District to assess the operational and financial performance of existing solar PV systems installed at three high schools and one middle school. In 2015, the District engaged Sage for the second phase of its energy project - 3.3 MW of solar PV at 16 middle and elementary schools, financed by Clean Renewable Energy Bonds (CREBs). Sage developed conceptual designs for each site to meet District preferences and performance goals. Working closely with financial advisors to the District, Sage performed detailed modeling in support of the CREBs Bond applications and issuance. Sage subsequently managed the competitive procurement process for the PV systems and has assisted with contract negotiations. Sage then provided design review and construction support for the project, which became operational in 2016.
SERVICES PROVIDED
Operational / Performance Guarantee Analysis
Feasibility Study
Financial & Performance Modeling
RFP / Vendor Selection
Contract Negotiation
Design Review
Construction Support
Commissioning Oversight
Operations & Asset Management